Counties / Texas
Brazoria County power projects
Brazoria County, Texas has 56 active power projects totalling 11,487 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 5,747 MW (50%). The largest single project is Hecate Energy Orem Wind (1,542 MW wind). 31 projects have signed an interconnection agreement or reached a later stage. 7 projects in the county are listed as withdrawn or cancelled.
Active projects
56
11.5 GW capacity
IA signed or later
31
55% of active projects
Withdrawn or cancelled
7
listed by ERCOT
Changes tracked
15
since Sep 2026
Changes in Brazoria County
New
10/01/2026
Myrtle Solar Repower · Solar · Brazoria County
Entered the queue at 42110 Angleton 138kV. Projected COD 06/21/2027.
+314 MW
New
10/01/2026
Bodkin BESS SLF · BESS · Brazoria County
Entered the queue at The 138kV Danbury Dab DANBUR_POI_8 (BUS#42875) Station. Projected COD 12/01/2027.
+0 MW
Withdrawn
Unconfirmed
10/01/2026
Bocanova Power II · BESS · Brazoria County
Missing from the latest report, not yet marked withdrawn by ERCOT.
−150 MW
COD change
10/01/2026
Cottonwood Bayou Solar · Solar · Brazoria County
Projected COD moved 08/29/2026 → 10/30/2026. Delay #1 for this project.
+2 mo
COD change
10/01/2026
Hastings Park BESS · BESS · Brazoria County
Projected COD moved 09/15/2027 → 02/27/2028. Delay #1 for this project.
+5 mo
COD change
10/01/2026
Elio BESS · BESS · Brazoria County
Projected COD moved 08/05/2028 → 12/31/2028. Delay #1 for this project.
+5 mo
COD change
10/01/2026
Dan Kearney BESS · BESS · Brazoria County
Projected COD moved 10/01/2027 → 02/28/2029. Delay #1 for this project.
+17 mo
COD change
10/01/2026
Goby Energy Center · BESS · Brazoria County
Projected COD moved 09/30/2027 → 09/07/2029. Delay #1 for this project.
+23 mo
COD change
10/01/2026
Friendswood Energy Storage · BESS · Brazoria County
Projected COD moved 09/30/2027 → 03/30/2028. Delay #1 for this project.
+6 mo
Stage change
09/18/2026
FIS Approved
Stage change
09/15/2026
FIS Approved
Stage change
09/10/2026
FIS Requested
All projects
For residents and landowners
- What power projects are planned in Brazoria County?
- ERCOT's October 2026 report lists 56 active projects in Brazoria County totalling 11,487 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.