Substation / point of interconnection ยท Brazoria County
39010 138kV HASTINGS
1 active project totalling 256 MW is queued to connect at 39010 138kV HASTINGS in Brazoria County, Texas, according to ERCOT's October 2026 report.
Active capacity
256 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 26INR0551 | Hastings Park BESS | BESS | 256 | IA Signed | 02/27/2028 | 1 |