Methodology

Data and methods

All project data comes from ERCOT's public Generation Interconnection Status (GIS) report, published monthly. Reports compared so far: September 2026, October 2026.

How changes are found

  • Projects are matched across reports by their INR number, never by name.
  • New: a project appears in a report for the first time. Its date is the earliest milestone ERCOT lists for it (the FIS request is often dated before the screening study start).
  • Stage change: dated by ERCOT's own milestone columns (FIS requested and approved, IA signed, approval for energization and synchronization). Planned future dates are ignored.
  • COD change and MW change: dated by the report that first shows the new value.
  • Withdrawn: the project appears on ERCOT's Inactive Projects or Cancellation Update sheet. A project that disappears from a report without either is marked unconfirmed until a later report confirms it.

Locations

ERCOT does not publish substation coordinates. The map places each substation near its county's centre, so positions are approximate. County boundaries come from US Census data.

Our estimates

Values we derive rather than read from ERCOT, such as a substation's withdrawal share, are labelled EST.

What we don't publish

We only use public reports. We do not publish interconnection study reports or any Critical Energy/Electric Infrastructure Information (CEII).

Known limits

  • Some projects list 0 MW in ERCOT's report, usually components of self-limiting facilities. We show them as ERCOT lists them.
  • Substation names are shown as ERCOT lists them and may include bus numbers. Where an entity left ERCOT's form placeholders in the name, such as <345kV>, we remove the angle brackets and keep the values.
  • The first two digits of an INR are part of ERCOT's request number. They do not show the year the request was filed.
  • Some active projects keep a projected COD that has already passed. Their pages are marked "COD date passed".