Texas grid · ERCOT interconnection queue
What changed in the Texas queue
In ERCOT's October 2026 report, 23 projects entered the Texas interconnection queue, 50 projects left it and 116 projects pushed back their commercial operation date. 1,789 projects totalling 438.8 GW are now waiting to connect.
New projects
+23
10.1 GW added
Withdrawn
−50
8.8 GW removed
COD delays
116
start date pushed back
Stage changes
74
moved to a later stage
October 2026 report by fuel
See all 299 changesNumber of projects with each kind of change. Click a row to see the projects.
| Change | BESS | Solar | Wind | Gas | Other | Total | Size |
|---|---|---|---|---|---|---|---|
| New projects | 3 | 12 | 2 | 4 | 2 | 23 | +10,066 MW |
| Withdrawals | 26 | 20 | 2 | 2 | · | 50 | −8,814 MW |
| Stage changes | 19 | 45 | 2 | 7 | 1 | 74 | 13 signed an IA |
| COD changes | 50 | 45 | 8 | 20 | 1 | 124 | 116 later, avg +11 mo |
| MW changes | 8 | 10 | 6 | 4 | · | 28 | net −1,938 MW |
The queue today, by stage
Active projects by the furthest milestone ERCOT lists for them.
| Stage | Projects | Capacity | Share of active MW |
|---|---|---|---|
| Screening | 31 | 6.8 GW | |
| FIS Requested | 1,028 | 273.2 GW | |
| FIS Approved | 104 | 18.5 GW | |
| IA Signed | 494 | 119.7 GW | |
| Energization Approved | 8 | 0.9 GW | |
| Sync Approved | 124 | 19.7 GW | |
| All active | 1,789 | 438.8 GW |