Counties / Texas
Wharton County power projects
Wharton County, Texas has 42 active power projects totalling 8,625 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 3,874 MW (45%). The largest single project is EmberGreen (1,036 MW natural gas). 24 projects have signed an interconnection agreement or reached a later stage. 1 project in the county is listed as withdrawn or cancelled.
Active projects
42
8.6 GW capacity
IA signed or later
24
57% of active projects
Withdrawn or cancelled
1
listed by ERCOT
Changes tracked
5
since Sep 2026
Changes in Wharton County
New
10/01/2026
Starfield Energy Storage · BESS · Wharton County
Entered the queue at Tap 138kV 44150 Hungerford - 44190 East Bernard. Projected COD 12/31/2030.
+122 MW
COD change
10/01/2026
TOCE BESS 1 · BESS · Wharton County
Projected COD moved 05/31/2028 → 12/31/2028. Delay #1 for this project.
+7 mo
COD change
10/01/2026
Cernan BESS · BESS · Wharton County
Projected COD moved 10/01/2027 → 10/02/2028. Delay #1 for this project.
+12 mo
Stage change
09/23/2026
FIS Approved
Stage change
09/23/2026
FIS Approved
All projects
For residents and landowners
- What power projects are planned in Wharton County?
- ERCOT's October 2026 report lists 42 active projects in Wharton County totalling 8,625 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.