21INR0505 · BESS · Wharton County
Ramsey Storage
Ramsey Storage is a 500 MW battery storage project in Wharton County, Texas, connecting at 44200 Hillje 345kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 06/30/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 21INR0505
- Capacity
- 500 MW
- Fuel
- BESS (BA)
- Substation
- 44200 Hillje 345kV
- County
- Wharton County
- Interconnecting entity
- Hecate Energy Ramsey Storage LLC
- Projected COD
- 06/30/2028
- Entered queue
- 05/20/2020
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/11/2022FIS Requested → IA Signed
- 12/23/2020Screening → FIS Requested
- 05/20/2020Entered the queue with 500 MW, projected COD 06/30/2028
Other projects at this substation
| Danish Fields Solar | Solar | 603 MW | Sync Approved |
| Voyager Storage | BESS | 50 MW | FIS Requested |
| Space City Solar | Solar | 366 MW | IA Signed |