LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
20INR0238 · BESS · Wharton County

Voyager Storage

Voyager Storage is a 50 MW battery storage project in Wharton County, Texas, connecting at 44200 Hillje 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/08/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
20INR0238
Capacity
50 MW
Fuel
BESS (BA)
Interconnecting entity
EDF Renewables Development, Inc.
Projected COD
04/08/2028
Entered queue
01/14/2019
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/26/2019
    Screening → FIS Requested
  • 01/14/2019
    Entered the queue with 50 MW, projected COD 04/08/2028

Other projects at this substation

Danish Fields SolarSolar603 MWSync Approved
Space City SolarSolar366 MWIA Signed
Ramsey StorageBESS500 MWIA Signed