20INR0238 · BESS · Wharton County
Voyager Storage
Voyager Storage is a 50 MW battery storage project in Wharton County, Texas, connecting at 44200 Hillje 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/08/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 20INR0238
- Capacity
- 50 MW
- Fuel
- BESS (BA)
- Substation
- 44200 Hillje 345kV
- County
- Wharton County
- Interconnecting entity
- EDF Renewables Development, Inc.
- Projected COD
- 04/08/2028
- Entered queue
- 01/14/2019
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/26/2019Screening → FIS Requested
- 01/14/2019Entered the queue with 50 MW, projected COD 04/08/2028
Other projects at this substation
| Danish Fields Solar | Solar | 603 MW | Sync Approved |
| Space City Solar | Solar | 366 MW | IA Signed |
| Ramsey Storage | BESS | 500 MW | IA Signed |