Substation / point of interconnection ยท Wharton County
44200 Hillje 345kV
4 active projects totalling 1,519 MW are queued to connect at 44200 Hillje 345kV in Wharton County, Texas, according to ERCOT's October 2026 report.
Active capacity
1,519 MW
queued at this substation
Active projects
4
4 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 20INR0069 | Danish Fields Solar | Solar | 603 | Sync Approved | 08/29/2026 | 0 |
| 21INR0505 | Ramsey Storage | BESS | 500 | IA Signed | 06/30/2028 | 0 |
| 21INR0341 | Space City Solar | Solar | 366 | IA Signed | 06/01/2027 | 0 |
| 20INR0238 | Voyager Storage | BESS | 50 | FIS Requested | 04/08/2028 | 0 |