25INR0582 · BESS · Wharton County

Maleza Storage II

Maleza Storage II is a 256 MW battery storage project in Wharton County, Texas, connecting at 44220 Julia 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/31/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0582
Capacity
256 MW
Fuel
BESS (BA)
Interconnecting entity
Brush Storage, LLC
Projected COD
12/31/2028
Entered queue
02/20/2024
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 02/20/2024
    Entered the queue with 256 MW, projected COD 12/31/2028