27INR0392 · BESS · Wharton County
Cernan BESS
COD delayed 1×
Cernan BESS is a 10 MW battery storage project in Wharton County, Texas, connecting at Hillje 345kV (#44200). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 10/02/2028. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0392
- Capacity
- 10 MW
- Fuel
- BESS (BA)
- Substation
- Hillje 345kV (#44200)
- County
- Wharton County
- Interconnecting entity
- Cernan BESS LLC
- Projected COD
- 10/02/2028
- Entered queue
- 01/30/2025
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 10/01/2027 → 10/02/2028 (+12 months)
- 12/30/2025FIS Approved → IA Signed
- 10/31/2025FIS Requested → FIS Approved
- 01/30/2025Entered the queue with 10 MW, projected COD 10/01/2027
- 01/30/2025Screening → FIS Requested
Other projects at this substation
No other projects at this substation.