LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0493 · Solar · Wharton County

PHOTON SOLAR 1 2 SLF

PHOTON SOLAR 1 2 SLF is a 236 MW solar project in Wharton County, Texas, connecting at 44880 Waterh_POI_5 345kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 05/11/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0493
Capacity
236 MW
Fuel
Solar (PV)
Interconnecting entity
GulfStar Power, LLC
Projected COD
05/11/2026
Entered queue
10/01/2021
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/31/2024
    Energization Approved → Sync Approved
  • 10/15/2024
    IA Signed → Energization Approved
  • 08/28/2024
    Screening → FIS Requested
  • 11/28/2022
    FIS Requested → FIS Approved
  • 10/01/2021
    Entered the queue with 236 MW, projected COD 05/11/2026
  • 10/01/2021
    FIS Approved → IA Signed

Other projects at this substation

PHOTON SOLAR 3 SLFSolar110 MWSync Approved
PHOTON SOLAR 4 SLFSolar106 MWSync Approved
PHOTON SOLAR REPOWERINGSolar0 MWIA Signed
PHOTON BESS REPOWERINGBESS306 MWFIS Approved