26INR0725 · BESS · Wharton County
PHOTON BESS REPOWERING
PHOTON BESS REPOWERING is a 306 MW battery storage project in Wharton County, Texas, connecting at 44880 Waterh_POI_5 345kV. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 08/17/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0725
- Capacity
- 306 MW
- Fuel
- BESS (BA)
- Substation
- 44880 Waterh_POI_5 345kV
- County
- Wharton County
- Interconnecting entity
- GulfStar Power, LLC
- Projected COD
- 08/17/2027
- Entered queue
- 10/07/2025
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/23/2026FIS Requested → FIS Approved
- 10/07/2025Entered the queue with 306 MW, projected COD 08/17/2027
- 10/07/2025Screening → FIS Requested
Other projects at this substation
| PHOTON SOLAR 3 SLF | Solar | 110 MW | Sync Approved |
| PHOTON SOLAR 1 2 SLF | Solar | 236 MW | Sync Approved |
| PHOTON SOLAR 4 SLF | Solar | 106 MW | Sync Approved |
| PHOTON SOLAR REPOWERING | Solar | 0 MW | IA Signed |