25INR0673 · Solar · Wharton County
PHOTON SOLAR 4 SLF
PHOTON SOLAR 4 SLF is a 106 MW solar project in Wharton County, Texas, connecting at 44880 Waterh_POI_5 345kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 05/11/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0673
- Capacity
- 106 MW
- Fuel
- Solar (PV)
- Substation
- 44880 Waterh_POI_5 345kV
- County
- Wharton County
- Interconnecting entity
- GulfStar Power, LLC
- Projected COD
- 05/11/2026
- Entered queue
- 11/28/2022
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 11/04/2024Energization Approved → Sync Approved
- 08/21/2024Screening → FIS Requested
- 06/25/2024FIS Approved → Energization Approved
- 11/28/2022Entered the queue with 106 MW, projected COD 05/11/2026
- 11/28/2022FIS Requested → FIS Approved
Other projects at this substation
| PHOTON SOLAR 3 SLF | Solar | 110 MW | Sync Approved |
| PHOTON SOLAR 1 2 SLF | Solar | 236 MW | Sync Approved |
| PHOTON SOLAR REPOWERING | Solar | 0 MW | IA Signed |
| PHOTON BESS REPOWERING | BESS | 306 MW | FIS Approved |