Substation / point of interconnection ยท Wharton County
#44060 Blue Substation 345kV
1 active project totalling 209 MW is queued to connect at #44060 Blue Substation 345kV in Wharton County, Texas, according to ERCOT's October 2026 report.
Active capacity
209 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 26INR0474 | Sorghum BESS | BESS | 209 | IA Signed | 12/01/2027 | 0 |