Counties / Texas
Milam County power projects
Milam County, Texas has 29 active power projects totalling 8,290 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 3,396 MW (41%). The largest single project is Sandow Lakes Energy Station (1,292 MW natural gas). 15 projects have signed an interconnection agreement or reached a later stage. 2 projects in the county are listed as withdrawn or cancelled.
Active projects
29
8.3 GW capacity
IA signed or later
15
52% of active projects
Withdrawn or cancelled
2
listed by ERCOT
Changes tracked
7
since Sep 2026
Changes in Milam County
COD change
10/01/2026
Eastbell Milam Solar · Solar · Milam County
Projected COD moved 10/31/2025 → 11/01/2026. Delay #1 for this project.
+12 mo
COD change
10/01/2026
Adelite Storage · BESS · Milam County
Projected COD moved 06/28/2027 → 04/20/2028. Delay #1 for this project.
+10 mo
COD change
10/01/2026
Obbligato BESS · BESS · Milam County
Projected COD moved 02/28/2029 → 02/28/2030. Delay #1 for this project.
+12 mo
COD change
10/01/2026
Eastbell Milam Solar II · Solar · Milam County
Projected COD moved 07/15/2026 → 11/01/2026. Delay #1 for this project.
+4 mo
MW change
10/01/2026
203 → 207 MW
Stage change
09/17/2026
FIS Approved
Stage change
09/16/2026
FIS Approved
All projects
For residents and landowners
- What power projects are planned in Milam County?
- ERCOT's October 2026 report lists 29 active projects in Milam County totalling 8,290 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.