Substation / point of interconnection ยท Milam County
345 kV Herndon Switch Substation (#3804)
1 active project totalling 196 MW is queued to connect at 345 kV Herndon Switch Substation (#3804) in Milam County, Texas, according to ERCOT's October 2026 report.
Active capacity
196 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 22INR0605 | Camino Santiago Solar | Solar | 196 | IA Signed | 09/01/2027 | 0 |