22INR0605 · Solar · Milam County

Camino Santiago Solar

Camino Santiago Solar is a 196 MW solar project in Milam County, Texas, connecting at 345 kV Herndon Switch Substation (#3804). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 09/01/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
22INR0605
Capacity
196 MW
Fuel
Solar (PV)
Interconnecting entity
Camino Solar Project, LLC
Projected COD
09/01/2027
Entered queue
09/02/2022
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/17/2026
    FIS Requested → FIS Approved
  • 12/06/2024
    FIS Approved → IA Signed
  • 01/05/2023
    Screening → FIS Requested
  • 09/02/2022
    Entered the queue with 196 MW, projected COD 09/01/2027

Other projects at this substation

No other projects at this substation.