Substation / point of interconnection ยท Milam County
#13430 Sandow Switch 138kV
1 active project totalling 1,292 MW is queued to connect at #13430 Sandow Switch 138kV in Milam County, Texas, according to ERCOT's October 2026 report.
Active capacity
1,292 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 27INR0071 | Sandow Lakes Energy Station | Gas | 1,292 | FIS Requested | 04/01/2028 | 0 |