23INR0502 · BESS · Milam County
Adelite Storage
COD delayed 1×
Adelite Storage is a 232 MW battery storage project in Milam County, Texas, connecting at Tap 138kV Thorndale North (bus #3659) – Rookie Switch (bus #3701). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 04/20/2028. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0502
- Capacity
- 232 MW
- Fuel
- BESS (BA)
- County
- Milam County
- Interconnecting entity
- Adelite Storage Project LLC
- Projected COD
- 04/20/2028
- Entered queue
- 06/27/2022
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 06/28/2027 → 04/20/2028 (+10 months)
- 08/27/2024FIS Approved → IA Signed
- 05/01/2024FIS Requested → FIS Approved
- 09/09/2022Screening → FIS Requested
- 06/27/2022Entered the queue with 232 MW, projected COD 06/28/2027
Other projects at this substation
No other projects at this substation.