27INR0494 · BESS · Milam County
Obbligato BESS
COD delayed 1×
Obbligato BESS is a 201 MW battery storage project in Milam County, Texas, connecting at Tap 138kV 120# TALBRTRIDG – 3683# MINERVA1_8. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 02/28/2030. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0494
- Capacity
- 201 MW
- Fuel
- BESS (BA)
- County
- Milam County
- Interconnecting entity
- Obbligato BESS, LLC
- Projected COD
- 02/28/2030
- Entered queue
- 06/09/2025
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 02/28/2029 → 02/28/2030 (+12 months)
- 06/09/2025Entered the queue with 201 MW, projected COD 02/28/2029
- 06/09/2025Screening → FIS Requested
Other projects at this substation
No other projects at this substation.