LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0494 · BESS · Milam County

Obbligato BESS

COD delayed 1×

Obbligato BESS is a 201 MW battery storage project in Milam County, Texas, connecting at Tap 138kV 120# TALBRTRIDG – 3683# MINERVA1_8. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 02/28/2030. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0494
Capacity
201 MW
Fuel
BESS (BA)
Interconnecting entity
Obbligato BESS, LLC
Projected COD
02/28/2030
Entered queue
06/09/2025
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 02/28/2029 → 02/28/2030 (+12 months)
  • 06/09/2025
    Entered the queue with 201 MW, projected COD 02/28/2029
  • 06/09/2025
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.