25INR0382 · Solar · Milam County
HappyDogSolar
HappyDogSolar is a 86 MW solar project in Milam County, Texas, connecting at Tap 345kV 3704 Hog Creek Switch – 3687 Bell County East Switch. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 08/04/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0382
- Capacity
- 86 MW
- Fuel
- Solar (PV)
- County
- Milam County
- Interconnecting entity
- Rosula Solar LLC
- Projected COD
- 08/04/2027
- Entered queue
- 05/25/2023
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/07/2025FIS Requested → FIS Approved
- 12/16/2024FIS Approved → IA Signed
- 05/25/2023Entered the queue with 86 MW, projected COD 08/04/2027
- 05/25/2023Screening → FIS Requested