1 active project totalling 106 MW is queued to connect at 3701 Rookie Switch 138 kV in Milam County, Texas, according to ERCOT's October 2026 report.

Active capacity
106 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
25INR0214Burgos SolarSolar106FIS Approved11/22/20270