ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0214 · Solar · Milam County

Burgos Solar

Burgos Solar is a 106 MW solar project in Milam County, Texas, connecting at 3701 Rookie Switch 138 kV. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 11/22/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0214
Capacity
106 MW
Fuel
Solar (PV)
Interconnecting entity
Twin Oaks Solar, LLC
Projected COD
11/22/2027
Entered queue
10/18/2022
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/14/2026
    FIS Requested → FIS Approved
  • 03/03/2023
    Screening → FIS Requested
  • 10/18/2022
    Entered the queue with 106 MW, projected COD 11/22/2027

Other projects at this substation