24INR0208 · Solar · Milam County
Eastbell Milam Solar II
COD delayed 1×
Eastbell Milam Solar II is a 151 MW solar project in Milam County, Texas, connecting at 345 kV Bell County East Switch (bus# 3687) - TNP One (bus# 39950) circuit 2. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 11/01/2026. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0208
- Capacity
- 151 MW
- Fuel
- Solar (PV)
- County
- Milam County
- Interconnecting entity
- Cattlemen Solar Park II LLC
- Projected COD
- 11/01/2026
- Entered queue
- 02/03/2022
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 07/15/2026 → 11/01/2026 (+4 months)
- 11/20/2024Energization Approved → Sync Approved
- 09/13/2024IA Signed → Energization Approved
- 02/01/2024FIS Requested → FIS Approved
- 10/25/2023FIS Approved → IA Signed
- 02/03/2022Entered the queue with 151 MW, projected COD 07/15/2026
- 02/03/2022Screening → FIS Requested
Other projects at this substation
| Eastbell Milam Solar | Solar | 245 MW | Sync Approved |