21INR0203 · Solar · Milam County
Eastbell Milam Solar
COD delayed 1×
Eastbell Milam Solar is a 245 MW solar project in Milam County, Texas, connecting at 345 kV Bell County East Switch (bus# 3687) - TNP One (bus# 39950) circuit 2. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 11/01/2026. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 21INR0203
- Capacity
- 245 MW
- Fuel
- Solar (PV)
- County
- Milam County
- Interconnecting entity
- EDP RENEWABLES NORTH AMERICA LLC
- Projected COD
- 11/01/2026
- Entered queue
- 10/10/2018
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 10/31/2025 → 11/01/2026 (+12 months)
- 11/01/2023Energization Approved → Sync Approved
- 10/13/2023IA Signed → Energization Approved
- 10/28/2022FIS Requested → FIS Approved
- 09/02/2022FIS Approved → IA Signed
- 04/23/2019Screening → FIS Requested
- 10/10/2018Entered the queue with 245 MW, projected COD 10/31/2025
Other projects at this substation
| Eastbell Milam Solar II | Solar | 151 MW | Sync Approved |