Eastbell Milam Solar

COD delayed 1×

Eastbell Milam Solar is a 245 MW solar project in Milam County, Texas, connecting at 345 kV Bell County East Switch (bus# 3687) - TNP One (bus# 39950) circuit 2. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 11/01/2026. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
21INR0203
Capacity
245 MW
Fuel
Solar (PV)
Interconnecting entity
EDP RENEWABLES NORTH AMERICA LLC
Projected COD
11/01/2026
Entered queue
10/10/2018
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 10/31/2025 → 11/01/2026 (+12 months)
  • 11/01/2023
    Energization Approved → Sync Approved
  • 10/13/2023
    IA Signed → Energization Approved
  • 10/28/2022
    FIS Requested → FIS Approved
  • 09/02/2022
    FIS Approved → IA Signed
  • 04/23/2019
    Screening → FIS Requested
  • 10/10/2018
    Entered the queue with 245 MW, projected COD 10/31/2025

Other projects at this substation

Eastbell Milam Solar IISolar151 MWSync Approved