Substation / point of interconnection ยท Milam County
345 kV Bell County East Switch (bus# 3687) - TNP One (bus# 39950) circuit 2
2 active projects totalling 396 MW are queued to connect at 345 kV Bell County East Switch (bus# 3687) - TNP One (bus# 39950) circuit 2 in Milam County, Texas, according to ERCOT's October 2026 report.
Active capacity
396 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 21INR0203 | Eastbell Milam Solar | Solar | 245 | Sync Approved | 11/01/2026 | 1 |
| 24INR0208 | Eastbell Milam Solar II | Solar | 151 | Sync Approved | 11/01/2026 | 1 |