Substation / point of interconnection · Milam County
Little Pond Switch (Bus #3377) – Hog Creek Switch (Bus #3704) 345 kV Line
1 active project totalling 846 MW is queued to connect at Little Pond Switch (Bus #3377) – Hog Creek Switch (Bus #3704) 345 kV Line in Milam County, Texas, according to ERCOT's October 2026 report.
Active capacity
846 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 29INR0120 | MilamStation Power Secured Gas Generation | Gas | 846 | FIS Requested | 09/25/2029 | 0 |