29INR0120 · Gas · Milam County
MilamStation Power Secured Gas Generation
MilamStation Power Secured Gas Generation is a 846 MW natural gas project in Milam County, Texas, connecting at Little Pond Switch (Bus #3377) – Hog Creek Switch (Bus #3704) 345 kV Line. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/25/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 29INR0120
- Capacity
- 846 MW
- Fuel
- Gas (CC)
- County
- Milam County
- Interconnecting entity
- LCC-TX8, LLC
- Projected COD
- 09/25/2029
- Entered queue
- 03/24/2025
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/12/2025Screening → FIS Requested
- 03/24/2025Entered the queue with 846 MW, projected COD 09/25/2029
Other projects at this substation
No other projects at this substation.