Sypert Branch Solar Project

Sypert Branch Solar Project is a 261 MW solar project in Milam County, Texas, connecting at Tap 345kV #3751 Scooter Switch - #3687 Bell County East Switch Ckt 2. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 04/30/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0070
Capacity
261 MW
Fuel
Solar (PV)
Interconnecting entity
Sypert Branch Solar LLC
Projected COD
04/30/2026
Entered queue
09/21/2021
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/12/2025
    Energization Approved → Sync Approved
  • 12/10/2025
    IA Signed → Energization Approved
  • 10/31/2024
    FIS Requested → FIS Approved
  • 10/12/2023
    FIS Approved → IA Signed
  • 04/28/2022
    Screening → FIS Requested
  • 09/21/2021
    Entered the queue with 261 MW, projected COD 04/30/2026