24INR0070 · Solar · Milam County
Sypert Branch Solar Project
Sypert Branch Solar Project is a 261 MW solar project in Milam County, Texas, connecting at Tap 345kV #3751 Scooter Switch - #3687 Bell County East Switch Ckt 2. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 04/30/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0070
- Capacity
- 261 MW
- Fuel
- Solar (PV)
- County
- Milam County
- Interconnecting entity
- Sypert Branch Solar LLC
- Projected COD
- 04/30/2026
- Entered queue
- 09/21/2021
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/12/2025Energization Approved → Sync Approved
- 12/10/2025IA Signed → Energization Approved
- 10/31/2024FIS Requested → FIS Approved
- 10/12/2023FIS Approved → IA Signed
- 04/28/2022Screening → FIS Requested
- 09/21/2021Entered the queue with 261 MW, projected COD 04/30/2026