24INR0169 · BESS · Milam County
Yaupon Storage SLF
Yaupon Storage SLF is a 0 MW battery storage project in Milam County, Texas, connecting at to Tap 345 kV Gibson Switch (3706) – TNP One (39950). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0169
- Capacity
- 0 MW
- Fuel
- BESS (BA)
- County
- Milam County
- Interconnecting entity
- Yaupon Solar, LLC
- Projected COD
- 07/01/2028
- Entered queue
- 11/10/2021
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/28/2023FIS Requested → IA Signed
- 01/10/2022Screening → FIS Requested
- 11/10/2021Entered the queue with 0 MW, projected COD 07/01/2028
Other projects at this substation