23INR0478 · BESS · Milam County
Rhoda Storage
Rhoda Storage is a 141 MW battery storage project in Milam County, Texas, connecting at Tap 138kV 32 Robertson - 64 Milano. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 08/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0478
- Capacity
- 141 MW
- Fuel
- BESS (BA)
- Substation
- Tap 138kV 32 Robertson - 64 Milano
- County
- Milam County
- Interconnecting entity
- Milam Energy, LLC
- Projected COD
- 08/01/2028
- Entered queue
- 03/18/2022
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/31/2025FIS Requested → IA Signed
- 03/18/2022Entered the queue with 141 MW, projected COD 08/01/2028
- 03/18/2022Screening → FIS Requested