1 active project totalling 500 MW is queued to connect at 3377 Little Pond Switch ( LTPSW) 345 in Milam County, Texas, according to ERCOT's October 2026 report.

Active capacity
500 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
n/a
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
26INR0630Betel Storage IBESS500FIS Requested08/12/20260