25INR0389 · BESS · Milam County
Stoneridge BESS
Stoneridge BESS is a 102 MW battery storage project in Milam County, Texas, connecting at Tap 345 kV 13429 SANDOW SWITCH - 7040 AUSTROP CKT 2. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/31/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0389
- Capacity
- 102 MW
- Fuel
- BESS (BA)
- County
- Milam County
- Interconnecting entity
- Stoneridge Solar, LLC
- Projected COD
- 12/31/2026
- Entered queue
- 03/09/2023
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/10/2025Energization Approved → Sync Approved
- 06/26/2025IA Signed → Energization Approved
- 09/06/2024FIS Requested → FIS Approved
- 04/19/2024FIS Approved → IA Signed
- 03/09/2023Entered the queue with 102 MW, projected COD 12/31/2026
- 03/09/2023Screening → FIS Requested