Wilbarger County power projects

Wilbarger County, Texas has 21 active power projects totalling 8,506 MW in ERCOT's interconnection queue as of the October 2026 report. Natural gas is the largest share at 5,207 MW (61%). The largest single project is Limitless Energy Hub I (1,238 MW natural gas). 8 projects have signed an interconnection agreement or reached a later stage. 3 projects in the county are listed as withdrawn or cancelled.

Active projects
21
8.5 GW capacity
IA signed or later
8
38% of active projects
Withdrawn or cancelled
3
listed by ERCOT
Changes tracked
0
since Sep 2026

Changes in Wilbarger County

No changes in the reports compared so far.

All projects

ProjectFuelMWSubstationStageCOD
Limitless Energy Hub IGas1,238Tap 345kV 6101 RILEY7A - 60505 EDITHCLA7B.IA Signed12/01/2028
Limitless Energy Hub IIGas1,238Tap 345kV 6101 RILEY7A - 60505 EDITHCLA7B.IA Signed12/01/2028
H&C WILBARGER POWER IGas1,026Tap 345kV 6101 RILEY7A - 60505 EDITHCLA7B.FIS Requested02/27/2032
H&C WILBARGER POWER IIGas1,026Tap 345kV 6101 RILEY7A - 60505 EDITHCLA7B.FIS Requested02/27/2032
TEXPOGas6806101 Riley 345 kVFIS Requested10/31/2027
Reunion SolarSolar601Tap 345kV #60504 Tesla Road to #6111 RileyFIS Requested07/01/2028
Poco Trail SolarSolar439Tap 345kV 6101 Riley - 1422 BowmanFIS Requested04/02/2029
Wander Waters BESSBESS30461001 JIMTREEC7A 345kVFIS Approved10/31/2027
Adamstown SolarSolar251tap 345kV 1730 West Krum - 6111 Riley Ckt 2IA Signed08/31/2027
Grayback SolarSolar222Tap 345kV 6101 RILEY7A - 60505 EDITHCLA7B.FIS Requested09/01/2029
Felix North SolarSolar2016101 Riley 345kVIA Signed12/31/2028
Felix East SolarSolar201The 345 kV Riley Substation (#6101); AEPIA Signed12/31/2028
Felix West SolarSolar2016101 Riley 345 kVIA Signed12/31/2028
Reunion StorageBESS200Tap 345kV #60504 Tesla Road to #6111 RileyFIS Requested07/01/2028
Dundee West WindWind146345 kV Riley Substation (#6101); AEPIA Signed12/31/2027
White Wing StorageBESS130Tap 345 kV (#60504) Tesla - (#6111) RileyFIS Requested07/01/2028
White Wing SolarSolar127Tap 345 kV (#60504) Tesla - (#6111) RileyFIS Requested07/01/2028
Felix StorageBESS100The 345 kV Riley Substation (#6101); AEPFIS Requested07/31/2027
Blue Summit Energy StorageBESS10061001 JIM TREECE 345kVSync Approved07/31/2026
Proteus Vernon Solar SLFSolar756060 Vernon 138kVFIS Requested02/18/2029
Proteus Vernon Storage SLFBESS06060 Vernon 138kVFIS Requested02/18/2029
Alamosa SolarSolar210Not listedWithdrawnn/a
Alamosa StorageBESS207Not listedWithdrawnn/a
Blue Summit repowerWind10Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Wilbarger County?
ERCOT's October 2026 report lists 21 active projects in Wilbarger County totalling 8,506 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.