25INR0416 · BESS · Wilbarger County
Proteus Vernon Storage SLF
Proteus Vernon Storage SLF is a 0 MW battery storage project in Wilbarger County, Texas, connecting at 6060 Vernon 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 02/18/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0416
- Capacity
- 0 MW
- Fuel
- BESS (BA)
- Substation
- 6060 Vernon 138kV
- County
- Wilbarger County
- Interconnecting entity
- Vernon Solar and Storage LLC (a Delaware LLC)
- Projected COD
- 02/18/2029
- Entered queue
- 03/27/2023
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/03/2023Screening → FIS Requested
- 03/27/2023Entered the queue with 0 MW, projected COD 02/18/2029
Other projects at this substation
| Proteus Vernon Solar SLF | Solar | 75 MW | FIS Requested |