Substation / point of interconnection ยท Wilbarger County

Tap 345kV 6101 RILEY7A - 60505 EDITHCLA7B.

5 active projects totalling 4,749 MW are queued to connect at Tap 345kV 6101 RILEY7A - 60505 EDITHCLA7B. in Wilbarger County, Texas, according to ERCOT's October 2026 report.

Active capacity
4,749 MW
queued at this substation
Active projects
5
5 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
27INR0581Limitless Energy Hub IGas1,238IA Signed12/01/20280
27INR0582Limitless Energy Hub IIGas1,238IA Signed12/01/20280
32INR0006H&C WILBARGER POWER IGas1,026FIS Requested02/27/20320
32INR0008H&C WILBARGER POWER IIGas1,026FIS Requested02/27/20320
28INR0464Grayback SolarSolar222FIS Requested09/01/20290