Substation / point of interconnection ยท Wilbarger County
The 345 kV Riley Substation (#6101); AEP
2 active projects totalling 301 MW are queued to connect at The 345 kV Riley Substation (#6101); AEP in Wilbarger County, Texas, according to ERCOT's October 2026 report.
Active capacity
301 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 27INR0007 | Felix East Solar | Solar | 201 | IA Signed | 12/31/2028 | 0 |
| 27INR0009 | Felix Storage | BESS | 100 | FIS Requested | 07/31/2027 | 0 |