ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0007 · Solar · Wilbarger County

Felix East Solar

Felix East Solar is a 201 MW solar project in Wilbarger County, Texas, connecting at The 345 kV Riley Substation (#6101); AEP. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/31/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0007
Capacity
201 MW
Fuel
Solar (PV)
Interconnecting entity
Felix 1, LLC
Projected COD
12/31/2028
Entered queue
12/22/2022
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 02/21/2025
    FIS Requested → IA Signed
  • 12/22/2022
    Entered the queue with 201 MW, projected COD 12/31/2028
  • 12/22/2022
    Screening → FIS Requested

Other projects at this substation

Felix StorageBESS100 MWFIS Requested