25INR0480 · BESS · Brazoria County
Bell Creek BESS
Bell Creek BESS is a 201 MW battery storage project in Brazoria County, Texas, connecting at Tap 138kV 39500 West Colombia - 39703 FM524. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 10/30/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0480
- Capacity
- 201 MW
- Fuel
- BESS (BA)
- County
- Brazoria County
- Interconnecting entity
- BELL CREEK BESS, LLC
- Projected COD
- 10/30/2027
- Entered queue
- 06/28/2023
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 11/14/2024FIS Approved → IA Signed
- 05/16/2024FIS Requested → FIS Approved
- 11/17/2023Screening → FIS Requested
- 06/28/2023Entered the queue with 201 MW, projected COD 10/30/2027