23INR0091 · Solar · Brazoria County

Cascade Solar

Cascade Solar is a 171 MW solar project in Brazoria County, Texas, connecting at 43180 SAVANAH 345 kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 01/15/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0091
Capacity
171 MW
Fuel
Solar (PV)
Interconnecting entity
Cascade Solar Energy, LLC
Projected COD
01/15/2028
Entered queue
02/09/2021
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/02/2025
    FIS Requested → FIS Approved
  • 04/17/2023
    FIS Approved → IA Signed
  • 04/28/2021
    Screening → FIS Requested
  • 02/09/2021
    Entered the queue with 171 MW, projected COD 01/15/2028

Other projects at this substation

No other projects at this substation.