30INR0073 · Gas · Brazoria County
Bulldog Power II
Bulldog Power II is a 311 MW natural gas project in Brazoria County, Texas, connecting at 39703 TNMP FM524 Substation 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/30/2030.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 30INR0073
- Capacity
- 311 MW
- Fuel
- Gas (GT)
- Substation
- 39703 TNMP FM524 Substation 138kV
- County
- Brazoria County
- Interconnecting entity
- Bulldog Power II LLC
- Projected COD
- 09/30/2030
- Entered queue
- 12/12/2025
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/12/2025Entered the queue with 311 MW, projected COD 09/30/2030
- 12/12/2025Screening → FIS Requested
Other projects at this substation
| Bulldog Power (TEF - Due Diligence) | Gas | 311 MW | FIS Approved |