19INR0041 · Solar · Brazoria County
Myrtle Solar
Myrtle Solar is a 321 MW solar project in Brazoria County, Texas, connecting at 42110 Angleton 138kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 06/21/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 19INR0041
- Capacity
- 321 MW
- Fuel
- Solar (PV)
- Substation
- 42110 Angleton 138kV
- County
- Brazoria County
- Interconnecting entity
- Myrtle Solar, LLC
- Projected COD
- 06/21/2027
- Entered queue
- 03/15/2017
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/20/2022Energization Approved → Sync Approved
- 12/07/2022IA Signed → Energization Approved
- 01/25/2022FIS Requested → FIS Approved
- 11/13/2019FIS Approved → IA Signed
- 05/09/2017Screening → FIS Requested
- 03/15/2017Entered the queue with 321 MW, projected COD 06/21/2027
Other projects at this substation
| Myrtle Solar Repower | Solar | 314 MW | FIS Approved |