19INR0134 · Solar · Brazoria County
Cottonwood Bayou Solar
COD delayed 1×
Cottonwood Bayou Solar is a 351 MW solar project in Brazoria County, Texas, connecting at tap 138kV 42870 Liverpool - 43070 Petson. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 10/30/2026. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 19INR0134
- Capacity
- 351 MW
- Fuel
- Solar (PV)
- Substation
- tap 138kV 42870 Liverpool - 43070 Petson
- County
- Brazoria County
- Interconnecting entity
- Cottonwood Bayou Solar, LLC
- Projected COD
- 10/30/2026
- Entered queue
- 09/22/2017
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 08/29/2026 → 10/30/2026 (+2 months)
- 05/29/2024Energization Approved → Sync Approved
- 05/01/2024IA Signed → Energization Approved
- 04/27/2023FIS Requested → FIS Approved
- 11/13/2019FIS Approved → IA Signed
- 02/15/2018Screening → FIS Requested
- 09/22/2017Entered the queue with 351 MW, projected COD 08/29/2026
Other projects at this substation