26INR0189 · BESS · Brazoria County
Skipjack Energy Storage
Skipjack Energy Storage is a 151 MW battery storage project in Brazoria County, Texas, connecting at Tap 138 42980 Nash - 44010 W A Parish ckt #2. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 02/28/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0189
- Capacity
- 151 MW
- Fuel
- BESS (BA)
- County
- Brazoria County
- Interconnecting entity
- Skipper Energy Storage LLC
- Projected COD
- 02/28/2028
- Entered queue
- 07/29/2023
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/13/2024FIS Requested → IA Signed
- 07/29/2023Entered the queue with 151 MW, projected COD 02/28/2028
- 07/29/2023Screening → FIS Requested