ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0189 · BESS · Brazoria County

Skipjack Energy Storage

Skipjack Energy Storage is a 151 MW battery storage project in Brazoria County, Texas, connecting at Tap 138 42980 Nash - 44010 W A Parish ckt #2. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 02/28/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0189
Capacity
151 MW
Fuel
BESS (BA)
Interconnecting entity
Skipper Energy Storage LLC
Projected COD
02/28/2028
Entered queue
07/29/2023
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/13/2024
    FIS Requested → IA Signed
  • 07/29/2023
    Entered the queue with 151 MW, projected COD 02/28/2028
  • 07/29/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.