26INR0226 · BESS · Brazoria County
First Capitol BESS
First Capitol BESS is a 258 MW battery storage project in Brazoria County, Texas, connecting at Tap 138kV West Columbia Main (39500) - Sweeny Cogen (110505). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 11/01/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0226
- Capacity
- 258 MW
- Fuel
- BESS (BA)
- County
- Brazoria County
- Interconnecting entity
- First Capitol BESS, LLC
- Projected COD
- 11/01/2027
- Entered queue
- 09/22/2023
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/15/2025FIS Requested → IA Signed
- 09/22/2023Entered the queue with 258 MW, projected COD 11/01/2027
- 09/22/2023Screening → FIS Requested