28INR0448 · BESS · Brazoria County

Gulf Prairie BESS

Gulf Prairie BESS is a 208 MW battery storage project in Brazoria County, Texas, connecting at (CEHESub) looped either 1) on 138 kV circuit 82 between RIWOOD (#43150) and Angleton (#42110), or 2) on 345 kV circuit 18 between DOW (#42500) and Huizache (#46640). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0448
Capacity
208 MW
Fuel
BESS (BA)
Interconnecting entity
Gulf Prairie Energy LLC
Projected COD
12/01/2028
Entered queue
09/03/2025
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/03/2025
    Entered the queue with 208 MW, projected COD 12/01/2028
  • 09/03/2025
    Screening → FIS Requested

Other projects at this substation

Gulf Prairie SolarSolar202 MWFIS Requested