25INR0235 · BESS · Brazoria County
Austin Bayou Storage I
Austin Bayou Storage I is a 151 MW battery storage project in Brazoria County, Texas, connecting at Tap 345 kV Savana 43180 to Seabreeze 43020 - Ckt 27. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 06/01/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0235
- Capacity
- 151 MW
- Fuel
- BESS (BA)
- County
- Brazoria County
- Interconnecting entity
- Austin Bayou Solar, LLC
- Projected COD
- 06/01/2027
- Entered queue
- 02/23/2023
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 02/14/2025FIS Requested → IA Signed
- 02/23/2023Entered the queue with 151 MW, projected COD 06/01/2027
- 02/23/2023Screening → FIS Requested
Other projects at this substation
| Austin Bayou Solar | Solar | 502 MW | IA Signed |
| Austin Bayou Storage III | BESS | 157 MW | IA Signed |