25INR0554 · BESS · Brazoria County
Dan Kearney BESS
COD delayed 1×
Dan Kearney BESS is a 204 MW battery storage project in Brazoria County, Texas, connecting at 39703 TNFM524 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 02/28/2029. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0554
- Capacity
- 204 MW
- Fuel
- BESS (BA)
- Substation
- 39703 TNFM524 138kV
- County
- Brazoria County
- Interconnecting entity
- Dan Kearney BESS LLC
- Projected COD
- 02/28/2029
- Entered queue
- 01/03/2024
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 10/01/2027 → 02/28/2029 (+17 months)
- 09/18/2026FIS Requested → FIS Approved
- 10/18/2024FIS Approved → IA Signed
- 01/03/2024Entered the queue with 204 MW, projected COD 10/01/2027
- 01/03/2024Screening → FIS Requested
Other projects at this substation
No other projects at this substation.