Substation / point of interconnection ยท Brazoria County
Tap 138kV 42110 Angleton - 43381 West Columbia
1 active project totalling 311 MW is queued to connect at Tap 138kV 42110 Angleton - 43381 West Columbia in Brazoria County, Texas, according to ERCOT's October 2026 report.
Active capacity
311 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 24INR0282 | Royal River BESS | BESS | 311 | IA Signed | 06/30/2028 | 0 |