27INR0209 · BESS · Brazoria County

Goby Energy Center

COD delayed 1×

Goby Energy Center is a 201 MW battery storage project in Brazoria County, Texas, connecting at Tap 138kV line 44390 Karsten - 44721 Thompsons. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/07/2029. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0209
Capacity
201 MW
Fuel
BESS (BA)
Interconnecting entity
Goby Energy Center
Projected COD
09/07/2029
Entered queue
05/07/2024
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 09/30/2027 → 09/07/2029 (+23 months)
  • 05/07/2024
    Entered the queue with 201 MW, projected COD 09/30/2027
  • 05/07/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.